Mohmand Dam

Name of Project : Mohmand Dam Hydropower Project (MDHP)
Location / Country : District Mohmand (Merged Area), Khyber Pakhtunkhwa / Pakistan
Client : WAPDA
Funded by : Ministry of Water & Power, Govt. of Pakistan
Commencement : December 2019
Completion : December 2026

MDHP is a multipurpose facility located about 5 km upstream of the existing Munda Headworks, with its dam site at a distance of about 48 km from Peshawar; and its reservoir area extending upstream to Mohmand and Bajaur Tribal Districts, in KP.

MDHP comprises of the following major components:

  • Main dam (CFRD) with 213 m height, 716 m crest length & 12 m width;
  • Two Diversion Tunnels, each 3,317 m long with 15 m dia, for 5,900 cumecs design flood;
  • Spillway of gated Ogee Weir type with a clear width of 105 m and capacity of 25,514 cumecs, with 7 No. radial gates each having a size of 15 m x 21 m;
  • Headrace Tunnel about 722 m long and 13.2 m dia;
  • Penstock about 406 m long with diameter varying from 4.9 to 10 m;
  • Open Air Surface Powerhouse (size 55 m x 157 m);
  • Tail Water Regulation Pond;
  • Transmission System;
  • Left Bank Irrigation Tunnel (4.3 Km long and 2.5 m dia);
  • Right Bank Irrigation Tunnel (3.0 Km long and 2.5 m dia);
  • Left Bank Irrigation Canal (12.4 Km long for 3.5 cumecs); and
  • Right Bank Irrigation Canal (14.75 Km long for 3.2 cumecs).

MDHP aims at accruing the following benefits:

  • Power generation of 800 MW, with 186 m gross head and 544 cumecs discharge;
  • Irrigated Agricultural development of 6,773 hectares;
  • Flood control with gross storage capacity of 1,596 MCM, live storage capacity of 834 MCM and Probable Maximum Flood of 27,427 cumecs;
  • Drinking Water Supply of 13.30 cumecs to Peshawar;
  • Annual Energy of 2,862 GWh / 3,051 GWh (with / without water supply to Peshawar); and
  • CCA on the Left Bank (3,649 hectare) and on the Right Bank (3,124 hectare).